Good afternoon, Diane
Your home is 64% complete — and on schedule.
Jasper, GA · 74°F · Clear
64% Complete
Currently underway
Insulation & Drywall
Phase 7 of 10 · Started Jul 7 · Est. complete Aug 1
Next: Interior Finishes & Cabinetry
JUL 6
Stone veneer — south elevation
From your team

“Framing inspection passed with no corrections — insulation crews start Monday. Weather looks great all week.”

CB
Cody Barnes · Site Superintendent
Next paymentDue in 7 days
$165,240
Draw 5 · Insulation & Drywall
Due Jul 15, 2026
Next on site
Drywall Inspection
Pickens County · Fri, Jul 10 · 9:00 AM
Then: Cabinet pre-install walk — Jul 23
SelectionsOver allowance
+$8,150
across 4 categories
Appliances and lighting are trending over; fixtures are under. Review before the next selection meeting.
Overall progress
Phase 7 of 10 · Insulation & Drywall
64%
Broke ground · Nov 2025Est. handover · Dec 2026
Site Evaluation & DesignComplete
Completed Aug 2025
Plans finalized, land surveyed, and budget locked to within ±3%.
Permitting & Site PrepComplete
Completed Oct 2025
County permits issued; driveway cut and building pad cleared.
Foundation & FootingsComplete
Completed Nov 2025
Footings poured and inspected; basement walls set and waterproofed.
FramingComplete
Completed Feb 2026
Full frame up; roof trusses set and sheathed.
Roofing & Dry-InComplete
Completed Mar 2026
Shingles on; windows and exterior doors installed and sealed.
Mechanical Rough-InComplete
Completed May 2026
Plumbing, electrical, and HVAC rough-ins passed inspection.
Insulation & DrywallIn Progress
In progress · Jul 2026
Insulation underway; drywall hangs the week of Jul 14.
Interior Finishes & CabinetryUpcoming
Aug – Sep 2026
Trim carpentry, cabinetry, and interior paint.
Flooring, Tile & FixturesUpcoming
Oct 2026
Your selections installed throughout the home.
Exterior, Landscaping & HandoverUpcoming
Nov – Dec 2026
Stone veneer, grading, final walkthrough, and keys.
All updates Exterior Interior Framing Systems
Exterior
Stone veneer — south elevation
Jul 6, 2026
Interior
Drywall delivered to site
Jul 6, 2026
Interior
Insulation — main level
Jul 3, 2026
Systems
Rough-in inspection passed
Jun 27, 2026
Systems
HVAC trunk lines set
Jun 20, 2026
Framing
Great room framing
Jun 5, 2026
Exterior
Roof dried-in
Mar 30, 2026
Foundation
Foundation walls poured
Nov 18, 2026
Site
Groundbreaking on your lot
Oct 30, 2026
Contract Total
$1,652,400
Paid to Date
$950,130
Remaining
$702,270
Selections
+$8,150
Paid to date$950,130 of $1,652,400
58% billed$702,270 remaining
Draw Schedule
DrawAmountStatusDate
1Deposit & Design
$165,240
Paid
Aug 2025
2Foundation
$206,550
Paid
Nov 2025
3Framing & Dry-In
$330,480
Paid
Mar 2026
4Mechanical Rough-In
$247,860
Paid
May 2026
5Insulation & Drywall
$165,240
Due Now
Due Jul 15
6Interior Finishes
$247,860
Upcoming
Est. Sep 2026
7Flooring, Tile & Fixtures
$148,716
Upcoming
Est. Oct 2026
8Final, Exterior & Punch
$140,454
Upcoming
Est. Dec 2026
July 2026
SMTWTFS
Scheduled event Today
Upcoming
JUL
10
Drywall InspectionInspection
Pickens County · 9:00 AM
JUL
14
Drywall Hang BeginsMilestone
Whitfield jobsite
JUL
23
Cabinet Pre-Install WalkWalkthrough
with Cody Barnes · 2:00 PM
AUG
06
Tile & Countertop ReviewSelection
Design Center, Canton · 10:30 AM
AUG
18
Lighting & Trim WalkthroughWalkthrough
Whitfield jobsite · 1:00 PM
All Contracts Plans Financial Permits
Construction Agreement
PDF · 2.4 MB · Executed Aug 12, 2025
Architectural Plans — Rev C
PDF · 18.1 MB · Jan 30, 2026
Selections Summary
PDF · 1.1 MB · Updated Jul 1, 2026
Allowance Schedule
XLSX · 240 KB · Jul 1, 2026
Building Permit — Pickens County
PDF · 820 KB · Oct 9, 2025
Draw 4 Statement
PDF · 460 KB · May 22, 2026